Posted By Shahril Othman 02-26-2020 09:01 PM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Sean, Not sure if this will help, but here are my thoughts: 1. Schedule Basis is explains how your schedule is derived and explains the logic behind, the assumptions and the contingencies built into your schedule. 2. Schedule management plan is how you would develop and control your schedule once ...
Posted By Shahril Othman 02-26-2020 08:40 PM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Fadi, I would try not to use a % for estimating cost of spares at the first instance. Here is what I would do: 1. Identify which major equipment require capital spares with consultation of the project and client team. Not all spares need to be purchased by the project. Some can be bought post-project ...