Posted By Peter Holroyd 12-05-2025 01:07 PM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Hi Group. WBS RP Draft.here are some comments.Presumably this document is meant to fit in a series of Breakdown Structure documents of which Organisation and Risk (OBS & RBS) have already been published. There are numerous other project breakdown structures within a project - contract, estimate, resource, ...
Posted By Peter Holroyd 11-02-2024 07:12 AM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Paul, totally agree about ACTUAL COSTS. We (the planners) just used the QS monthly CVR Report as in the end they have to align. Peter

EVM

Posted By Peter Holroyd 10-31-2024 12:58 PM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Kyle, I've read your discussions on the site. We used to run EV (Budget) till the 80% mark and then developed a company wide burn down database using an open database product (JIRA). Totally flexible, multiuser and handled all reports. I attach a paper I put together (personal use) on the generalised ...
Posted By Peter Holroyd 10-31-2024 12:57 PM
Found In Library: Productivity, Performance, & Earned Value