  • 1.  Data Sources

    Posted 07-01-2019 10:56 AM
    ​For what it's worth my client pays for a service/database provided by a firm "IPA"  Capital Projects Services & Consulting | Independent Project Analysis - IPA.
    This tailored industry-specific data is useful as an educated guess when developing project estimates, cost and schedules.

    ------------------------------
    [JJ] [Aucoin, PMP]
    [Project Controls]
    [Critical Path Planning]
    [Geismar] [La]
    ------------------------------


  • 2.  RE: Data Sources

    Posted 07-02-2019 08:23 AM
    I see RSMeans used a lot in the US government  sector with mixed results. The Estimator must dig into RSMeans and really work for the estimate. Factors like confined space, over head work, etc are a big part of adjusting the basic installation costs. But it's a starting point that the government will use to help determine reasonableness.

    ------------------------------
    Stephen Beck CCP
    Vice President, Project Controls and Change Management
    CRC Technologies, Inc.
    Knoxville TN