Arun - A prudent option is to start with a solid baseline, not based on early start activities, ideally based on levelled starts, and to routinely obtain a SPI >1.0, one can schedule the work as all "late start"; but, if the SPI goes < 1.0, the schedule could be a train wreck (late). Is your schedule resource loaded?
------------------------------
Anthony Woodrich
Senior Vice President
Administrative Controls Management, Inc
Ann Arbor
amw@acmpm.com------------------------------
Original Message:
Sent: 03-12-2025 11:05 AM
From: Arun Nair
Subject: Recommended practice for aligning SPI for In progress activities post Re-Baseline
Hi All,
At the time of re-baselining a project in Primavera, what is the best practice for maintaining an SPI of 1.
The concern is for in progress activities where Performance % complete is not equal to the Schedule % complete .
Is splitting of the activity recommended or is there any other option.
Thank you
------------------------------
[Arun] Nair]
Forensic Scheduler
[GTA] [Ontario]
[+1-7059915108]
[arunnair01@gmail.com]
------------------------------