Arun - A prudent option is to start with a solid baseline, not based on early start activities, ideally based on levelled starts, and to routinely obtain a SPI >1.0, one can schedule the work as all "late start"; but, if the SPI goes < 1.0, the schedule could be a train wreck (late). Is your schedule resource loaded?
------------------------------
Anthony Woodrich
Senior Vice President
Administrative Controls Management, Inc
Ann Arbor