Posted By Yahya Khatib 05-09-2018 08:23 AM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
​Hi Ty Moore Thank you for the reply that was helpful to me. Agreeing with what you stated that EVM for cost reimbursable contracts is similar to other projects with few "additional considerations". And while you have stated the main considerations in your reply. Do you know/recommend any industry ...
Posted By Yahya Khatib 05-02-2018 05:07 AM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Dear Anderson, Thanks for you input, the template you provided can help me to present my clarification. I have done some modifications to explain what I mean. For the attached sheet, upon completing 480 unit of the quantities out of 1000, the baseline was changed to 1100 and the installed quantity ...
Posted By Yahya Khatib 04-30-2018 04:14 PM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Greetings, We are working for a client PMO for a program of cost reimbursable projects. The PMO is newly established while projects are almost 60% completed in construction and 90% in Engineering. Our Construction Management Consultant (who is also responsible for cost control) is arguing that Earned ...
Posted By Yahya Khatib 03-07-2018 07:34 AM
Found In Egroup: Productivity, Performance, & Earned Value
\ view thread
Hi Sami That was very helpful ------------------------------ Yahya Al-Khatib CEP PSP Sr. PMO Planner Khatib & Alami Khobar +966541127560 ------------------------------