Hello Paula,
Sorry for the delayed response. Rules of credit apply to EVT 0/100, 25/50/75/100, 33/66/100 (in engineering do not every use 99%, it will never go past that!), 50/50. I have used these in all types of programs including Agile, research and development, LRIP, manufacturing, construction, logistics, and design. They are very much focused on the duration of the activities and the relationship to the reporting calendar, when the scope is hard to objectively take % on.
What are you looking for specifically?
------------------------------