There are several issues when trying to use P6 for EV calculations, some of which are outlined in my paper in the link below that compares P6, MSP and Asta Powerproject:
https://eastwoodharris.com/comparison-of-microsoft-project-oracle-primavera-p6-and-elecosoft-asta-powerproject/
Unfortunately, although P6 called construction scheduling software it lacks a large amount of functionality I expect to see in such an expensive piece of software that are found in other software packages like Powerproject.
The P6 EV functions in my opinion are very weak and before I retired last year all my construction industry customers who conducted EV exported the raw data from P6 to other software packages to perform their EV calculations due to the lack of EV reporting functionality in P6.
------------------------------
Paul Harris
Retired
Templestowe VIC, Australia
------------------------------
Original Message:
Sent: 10-18-2025 08:31 AM
From: Vladimir Liberzon
Subject: Improving Earned Value Tracking for Unit Rate Contracts in Scheduling Software
Hello Mohammed,
We use Spider Project and enter not mythical percent complete but actual physical volumes that were done, duration spent, materials consumed, etc. that are not always proportional. No problems with Earned Value or any other performance analysis methods.
------------------------------
Vladimir Liberzon
General Manager
v.liberzon@gmail.com
------------------------------