  • 1.  Primavera P6 v20 logic to milestones

    Posted 11-16-2022 08:29 AM
    I was in a review for EV compliance yesterday and asked about the excessive SS and FF relationships that tripped the threshold.  The response, "P6 does not allow you to use FS for successors on a start Milestone nor a FS as a predessor to a finish milestone.  I logged into Oracle and confirmed the new release has "eliminated the use of incorrect logic to milestones". 

    Does this mean we need to reconsider all RP, thresholds, metrics, and compliance?

    Thoughts?

    ------------------------------
    Michael Marcell EVP PSP
    Vice President
    K2 Consulting
    Bethesda MD
    (240) 876-4833
    ------------------------------


  • 2.  RE: Primavera P6 v20 logic to milestones

    Posted 11-17-2022 01:20 PM
    Hi, yes I noticed this recently when running Acumen Fuse to assess a schedule health. Noting so far I think its just a P6 thing perhaps health check tools is the first change to happen...Dan

    Daniel Foster
    Managing Principal Partner
     
    Skeiny
    Call Me: +61 0406 403 816 Email Me: Dan@skeiny.com.au Interact with Us:  
    <h></h>







  • 3.  RE: Primavera P6 v20 logic to milestones

    Posted 11-18-2022 12:28 PM
    FYI, we have been using the new OPC (cloud version) for a few months now and the milestone assignments are automatically SS for start milestones and FF for finish milestones. It is nice the errors don't come up in the schedule log and have to come back to fix as I did in v.20